As we look a head at the schedule we are at a point that we can actually start to identify a completion date...at least as defined by receiving a "Certificate of Occupancy" from the county.
The CO is important for a couple of things; it allows us to live in the house, but it also allows us to move from construction to long term financing with a lower interest rate.
This does not necessarily mean everything will be done, it probably won't. For example, the house interior doesn't need to be painted or the base/case trim installed, although we hope we are completed with those be for calling for the CO inspection.
The planning of the work for Marlys and I each weekend becomes more critical as we get to this crunch time, as the sequencing becomes critical and we don't want to be the hold up. For example; the tiling and hardwood flooring is scheduled to start a week from today, but if I don't have the upstairs walls/ceiling primed by then it can't.
Some items we have been working, e.g. exterior trim painting, may need to slip on the schedule because they are not in the critical path at this point.
As you look at the list you may also notice that it is starting to take on the feel of a "punch list" or the individual items that need to be completed vs. a project orientation. This is a result of where we are at in the process more then anything else.
- Seal deck posts and railings
- Sheetrock & Taping
- Frame Fireplace seat
- Prime Upstairs
- Power Hook-up to furnace and two outlets
- Tile, Hardwood Flooring & Carpet
- Build Stair Rail
- Garage Door Installation
- Trench for tanks and pitless adapter
- Cistern install
- Install Propane Tank
- Final Grade Site
- Furnace Hook-up
- Buy Appliances
- Bury Telephone Wire
- Sand and finish interior doors
- Finish Fireplace-Heat n glo Pier & Built in vacuum
- Finish Trim and Ceiling Liner
- Finish Carpentry Start
- Pour Patio
- Stone Veneer & Fireplace
- Rear Door Deck
- Appliances on site
- Kitchen cabinets deliver, install starts
- Road Work
- Prime Downstairs
- Countertops templated
- Purchase Light Fixtures
- Master Bath Mirror
- Finish Electric, Plumbing, Heating
- CO Inspection
- Paint Fascia
Although these are somewhat in order, the words on this page do not reflect the amount of work that is needed to complete the task. I have already also thought of a couple of items that need to be added, e.g. buy/install shower doors. I guess what I am saying is that the list will shrink and grow at the same time.
1 comment:
HI....I don't see very many "buy" & "decorate" items on the punch list....that is my area of expertise and I'm happy to help spend your money. Bill excels in the "do, fix, build" items!
Looks like there is light at the end of the tunnel!
Post a Comment